Probe into blast at Medupi power plant reveals procedural non-compliance

An investigation into a blast at the Medupi Power Station has revealed procedural non-compliance.
Unit four at the plant exploded in August, a month after its completion.
Nine employees on line management level have been suspended.
The area where unit four is situated is slightly quieter than the other units as it has been lying dormant for over nine months.
The unit contributes about 720 megawatts to the national grid.
Medupi’s Acting General Manager Zweli Witbooi said having this unit out takes a significant toll on the national grid.
“In terms of stages, if you are at stage 1 and you lose a Medupi unit, it takes you to stage 2.”
Eskom has estimated that the refurbishment of the unit will cost about R2.5 billion but that is subject to the awarding of a contract.
The utility plans to have the unit completed by August 2024.
-EWN
In other news – WATCH: Inside Tamia and her new born baby’s heart-melting homecoming
Royal AM chairperson, Andile Mpisane and his wife Tamia, are on cloud nine following the arrival of their newborn baby Miaandy Aliya Mpisane. Tamia confirmed her pregnancy in February, after she took to her Instagram account to share a breathtaking picture of her revealing her baby bump.
The influencer had been mum on rumors surrounding her pregnancy, but in February she finally decided to let the cat out of the bag. Learn More