Eskom’s power problem could get a whole lot worse

An electricity-supply crisis is looming in South Africa that could make intermittent outages in the past few months seem trivial by comparison.

Eskom, which supplies almost all the nation’s power, will lose more than a quarter of its current generating capacity over the next decade as it shuts ageing coal-fired plants. Replacing that output and adding capacity needed to meet rising demand will take years and cost more than R1 trillion, according to government estimates.

The problem is likely to worsen exponentially after 2030 as more plants reach retirement age.
While Eskom is building two new plants, Medupi and Kusile, they are running years behind schedule and billions of rand over budget, and won’t be enough to plug the supply gap. The utility has limited scope to invest in more projects because it isn’t making enough money to cover its operating costs and service its debt, which had ballooned to R419 billion at the end of its last financial year.

IPP project at Eskom

The government has said it will look to private investors to help fund new plants and step up purchases of renewable energy from independent producers, which have added 3 876 megawatts of capacity to the national grid since 2011. However, those plans are being implemented too slowly and on an insufficient scale, according to Jesse Burton, a researcher at the University of Cape Town’s Energy Research Centre.

“There’s this inaction by the state,” Burton said by phone. “We should be procuring immediately.”

President Cyril Ramaphosa in February announced plans to split Eskom into generation, transmission and distribution units — a move that should make it easier for private power producers to access the grid and sell their output. But powerful labor unions have vowed to prevent a break-up, fearing it will lead to job losses and privatisation. With elections due next month, the government has been loath to confront them head-on.

Also you may like…Home Affairs offline for 3 weeks due to technical faults

Computers at Home Affairs offices in Durban were offline for more than three weeks, leaving members of the public frustrated as they returned time and again only to be told they could not be helped.

Home Affairs spokesperson David Hlabane said the reason their computers were offline was due to an upgrade conducted on the Live Capture System for smart card identity documents and passports… Read more here

Back to top button